Benning Park Recreation Center (Ward 7)

Benning Park Recreation Center

Project Overview

Department of General Services (DGS) in partnership with the Department of Parks and Recreation (DPR) will work with the community to develop a scope of work to renovate the existing Bennning Park Recreation Center. Renovations may include but not be limited to ADA enhancements, interior and exterior site enhancements.  

Project Details

Project Address:  Southern Avenue and Fable Street, SE | 20019
Project Ward:  7
Project Budget:  $5 Million
DGS Project Manager:  Cynthia McClendon
DPR Project Manager: Peter Nohrden
Architect:  Moody Nolan
General Contractor:  TBD
Project Start Date: April 2016
Project Completion Date: Summer 2017 (tentative)
Project Status: In-Design

Next Meeting

Benning Park Recreation Center Community Meeting Flyer (March 2017)