Project Overview:
Project scope will include renovations to playgrounds with new playground equipment for 2-5 year olds and 6-12 year olds. A new recirculating splash pad will be provided that utilizes captured rainwater from the site to supply make-up water. Minor site accessibility upgrades will be performed where necessary for the new areas.
Project Details:
Project Name: Fort Davis Playground Modernization
Address: 1400 41st Street, SE
Ward: 7
DPR Project Manager: Brent Sisco
DGS Project Manager: Haniska Prinston & Stephon Heyer
Project Status: Construction
Project Delivery: Design/Build
Architect: Oculus Architects/Cefas Engineering
General Contractor: NVS Construction Company
Current Budget: $ 1,792,000
Start Date: Fall 2018
End Date: August 2019
DGS Contact: Wayne Gore
Presentations:
- Fort Davis Community Meeting Presentation (July 12, 2018)
- Fort Davis Community Meeting Presentation - March 12, 2015