Sorry, you need to enable JavaScript to visit this website.

dgs

Department of General Services
 

DC Agency Top Menu

-A +A
Bookmark and Share

Edgewood Recreation Center

Edgewood Recreation Center

Project Overview: 

This project will consist of the demolition of the existing community center building and construction of a new, larger, recreation center with a rooftop urban farm. The site will be renovated with new ADA accessible routes, new playgrounds and equipment, addition of a splash pad water feature, walking trail and a new grass athletic field. Project will also include a full-sized gymnasium. This will be a LEED Silver project.

Project Details:

Project Address:  3rd Street NE & Evarts Street, NE
Project Ward:  5
Project Budget:  $20.9M
DGS Project Manager:  Mark Bacus
DPR Project Manager:  Brent Sisco
Architect:  Moody Nolan Architecture
General Contractor: BuleSky/Coakley Williams
Project Start Date: Winter 2017
Project Completion Date: December 2019
Field Completion Date: Winter 2019
Status: Construction
Project Delivery: Design-Bid-Build
DGS Contact : Wayne Gore

Construction Updates:

Presentations:

Related Information: