Hearst Park and Pool Improvement Project

Project Description

The project will include design and construction including, but not limited to, new playground area, new tennis courts, renovation or replacement of existing soccer fields, new pool and pool house, ADA renovations to site, storm water management, remediation of site drainage, runoff, erosion issues, landscaping, fencing, site furnishings amenities, signage and hardscaping.

Project Details

  • Location: Ward 3
  • Construction Agency -  DGS
  • Design Start date  (Park and Pool) –  April 2016
  • Design Completion Date – Winter 2016
  • Construction Start date - Park  - Winter 2017
  • Construction Completion date – Park – Fall 2017
  • Construction Start Date -Pool – Fall 2018
  • Construction Completion Date – Pool Spring 2019
  • DGS Project Manager: Tim Craft
  • DPR Project Manager: Marshella Wallace
  • Status: Design
  • Architect: Cox Graae + Spack Architects
  • General Contractor: TBD
  • Budget: Park - $8 Million in FY15-FY17; Pool - $5 Million in FY19
  • DGS Contact: Jackie Stanley (DGS), (202) 431-1195