DPW Salt Storage Facility

Salt Storage Facility

Project Overview

This new 7,500 tons cacapity Salt Storage Facility will replace the existing DPW Salt Dome, which is under demolition for the United Soccer Stadium project at Buzzard Point.  
 

Project Details

  • Location: 2750 South Capitol Street, SE
  • Ward: 8
  • Construction Agency: DC Department of General Services
  • General Contractor: Consys, Inc.
  • Architect: Istudio Architects
  • DGS Project Manager: Hares M. Sayed
  • Green Features/LEED Certification: N/A
  • Project Start Date: January 20, 2016
  • Project Completion Date: September 30, 2016
  • Project Status: Construction in progress
  • DGS Contact: Hares Sayed, (202) 841-6269