BRENTWOOD RECREATION CENTER

Project Description:

This project will focus on improving the building’s functionality, accessibility, safety, and overall user experience so the facility can better support the current and future needs of the community. Planned improvements include reconfiguring and upgrading key interior spaces such as the entry vestibule, kitchen area, arts and crafts room, and restrooms. The project will also address code compliance needs and interior finishes that no longer meet current standards. 

Project Details:

Address: 2311 14th Street, NE
Ward: 5
DPR Project Manager: Bria Wigfall
DGS Project Manager: Ardavan Tookaloo
Project Status: We are at the end of the design development phase. Demo is scheduled to start end of December 2026.
Design Start Date: Summer 2026
Design End Date: winter 2026
Project Delivery: Design-Build
Architect/General Contractor: Atmos Solutions, Inc.
Architect: Atmos Solution Inc
General Contractor: Atmos Solution Inc
Current Budget: $2.6M
Construction Start Date: April, 2026
Construction End Date: June, 2027
DGS Contact: Brittany Hughes