Project Description:
This project will make improvements to the green space along Riggs Road and South Dakota Avenue NE. Park improvements may include new pathways, seating, landscaping, furnishings, and other amenities desired by the community.
Project Details:
Address: Riggs Road & South Dakota Avenue, NE
Ward: 5
DPR Project Manager: Shayda Musavi and Riley Piva
DGS Project Manager: Victor Medina
Project Status: Design
Design Start Date: 3/25/2025
Project End Date: 5/29/2026
Project Delivery: Design-Build
Architect: Greening Urban
General Contractor: Atmos Solutions Inc.
Current Budget: $337,500.00
DGS Contact: Charlee Bell
Presentations:
- Riggs & South Dakota Park Community Meeting Presentation - August 26, 2025
- Riggs & South Dakota Park Community Meeting Presentation - May 20, 2025
- Riggs & South Dakota Park Community Meeting Presentation - September 24, 2024