Project Description:
Park improvements. The final scope of work for this project is still TBD pending community outreach.
Project Details:
Address: 19th & L Street, NE
Ward: 5
DPR Project Manager: Shayda Musavi and Riley Piva
DGS Project Manager: Victor Medina
Project Status: Design
Design Start Date: Spring 2025
Design End Date: Summer 2025
Project Delivery: Design-Build
Architect: Greening Urban
General Contractor: Atmos Solutions Inc.
Current Budget: $337,500.00
Construction Start Date: Fall 2025
Construction End Date: Early Winter 2025
DGS Contact: Charlee Bell