Fletcher Johnson Abatement and Demolition

Project Description:

The St. Elizabeth’s East Sycamore Dr. Infrastructure project scope involves the construction of approximately 1,200 LF of new infrastructure and roadway. 

includes new underground wet and dry utilities along with new roadway and streetscape improvements as part of the redevelopment of the historic St. Elizabeth’s East Campus. This project connects the recently constructed 13th St SE with Alabama Ave SE, improving the flow of traffic through the campus and facilitating future development

Project Details:

Address: 4650 Benning Rd. NE 
Ward: 7
DGS Project Manager: Kevon Levenberry 
Client Agency Project Manager: Ketan Gada 
Project Delivery: DBB
Status: Design
Architect: AMT 
General Contractor: United Construction Services  
Current Budget: $8,489,304.10
Start Date: January 15,2025
End Date: September 30,2026
DGS ContactBrittany Hughes