Hill East 72" Storm Water Relocation

Project Description:

The Hill East Phase II project encompasses the relocation of a critical 72-inch combined sewer line, along with related infrastructure improvements, to accommodate the planned redevelopment of the Hill East site—formerly part of the District of Columbia General Hospital campus. This relocation is essential to support future mixed-use development while maintaining uninterrupted service of the city's sanitary and stormwater conveyance system.

Project Details:

Address:Hill East Phase II Site, Southeast Washington, D.C.
Ward: 7
DGS Project Manager: Renee Holmes
Client Agency: District of Columbia Water and Sewer Authority (DC Water)
General Contractor:Fort Myer Construction Company
Current Budget: $32M
Design Engineer:VIKA
Start Date: Summer 2025
End Date: Winter 2026