Project Description:
Renovation and repurposing of the Joy Evans Therapeutic Recreation Center. This includes renovations of the therapeutic pool, locker room, activity / therapy spaces, kitchen, bathrooms, lobby / meeting areas, in order to accommodate the heavy use load on the building. Also included are renovations to the adjacent campus for outdoor sports and activities. The idea is to turn this building / area into the premier therapeutic center in the District.
Project Details:
Ward: 7
Location: 3030 G Street, SE
DPR Project Manager: Brent Sisco
DGS Project Manager: Michael Etherton
Project Status: Construction
Architect: DLR group
General Contractor: Smoot Construction
Budget: $40.4M
Start Date: Spring 2022
End Date: Fall 2024
DGS Contact: Lawrence Davin
Presentations:
- Joy Evans Therapeutic Recreation Center Community Meeting Recording Link - March 29, 2022
- Joy Evans Therapeutic Recreation Center Community Meeting Presentation - March 29, 2022
- Joy Evans Therapeutic Recreation Center Community Meeting-May 13, 2021 Recording Link
- Joy Evans Therapeutic Recreation Center Community Meeting - May 13, 2021
- Joy Evans Therapeutic Recreation Center Community Meeting - July 30, 2020
- Joy Evans Therapeutic Recreation Center Community Meeting - June 30, 2020
Related Information: