Sorry, you need to enable JavaScript to visit this website.

dgs

Department of General Services
 

DC Agency Top Menu

-A +A
Bookmark and Share

New York Avenue Playground

Project Overview:

The proposal is to assess and replace damaged, outdated and hazardous playground equipment and accessories in the playground area(s), remove and haul away existing playground surfacing material and furnish and install new playground equipment, Poured in Place (PIP) Rubber, and furnish and install picnic benches.

Project Details:

Address: 100 N St. NW
Ward: 5
DPR Project Manager:Peter Nohrden
DGS Project Manager: Haniska Prinston
Project Status: Complete
Project Delivery: Design-Build
Landscape Architect: lee and associates, Inc.
General Contractor: BEDD Group, Inc.
Current Budget: $500,000
Start Date: September, 2020
End Date: January, 2021
DGS Contact: Wayne Gore

Presentations:

Related Information: