Project Description:
The St. Elizabeth’s East Sycamore Dr. Infrastructure project scope involves the construction of approximately 1,200 LF of new infrastructure and roadway.
includes new underground wet and dry utilities along with new roadway and streetscape improvements as part of the redevelopment of the historic St. Elizabeth’s East Campus. This project connects the recently constructed 13th St SE with Alabama Ave SE, improving the flow of traffic through the campus and facilitating future development.
Project Details:
Address: 2730 Martin Luther King Jr. Ave SE
Ward: 8
DGS Project Manager: Kevon Levenberry
Client Agency Project Manager: Latrena Owens
Project Delivery: DBB
Status: Design
Architect: Jacobs
General Contractor: United Construction
Current Budget: $20,0000,000
Start Date: August 2026
End Date: April 2027
DGS Contact: Kevon Levenberry