The Department is issuing this RFP to engage a Design-Builder to modernize Houston Elementary School, located at 1100 5oth Place, NE. The Project includes, among other things design, preconstruction and construction services to modernize the existing facility to accommodate an increased enrollment of between 336 students and 400 students by School Year 2025-2026. It is contemplated that the students will swing on site in trailers during the modernization .. The Project shall be designed in such a way so as to achieve, at a minimum, LEED BD+C Schools - Gold certification. The final Design Development submittal is required by March 19, 2018 and Construction Documents
submittal is required by June 11, 2018. The Project shall be Substantially Completed by July 15, 2020 (the "Substantial Completion Date")
DCAM-17-CS-0127- Design-Build Services for Houston ES Modernization
Tuesday, September 12, 2017