Project Overview

Construction of a new ~17,500 SF community center, park and playground on the 6.2-acre Parcel 6 (South parcel) of the historic McMillan Slow Sand Filtration Site. Scope also includes stabilization, preservation, and restoration of the historic assets inside the north and south service courts including all sand bins, sand washers, and regulator houses. Additional historic preservation and restoration will be completed on a portion of filter Cell 28, and all portal walls along the south service court. Demolition of parcels 1-7 as necessary to allow for future development.

Project Details

Location: 2501 North Capitol Street NW
Ward: 5
Construction Agency:  DGS
Program Agency: DPR
DPR Project Manager: Brent Sisco
DGS Project Manager: Gareth Thomas
General Contractors: Gilbane
Architect: TBD
Budget: $63 Million
Start Date – TBD
Completion Date – Summer 2019
Status: The larger development, which includes demolition and new construction, is on hold pending resolution of the court of appeals ruling issued on 12/9/16. DGS are proceeding with procurement of the stabilization and restoration scope of the historic assets (20 x Sand Bins, 4 x Regulator Houses, and 10 Sand Washers). Expected start on site date Summer 2017.
DGS Contact – Jackie Stanley

McMillan Stabilization & Restoration Community Update Meeting (February 2, 2017)

Existing Site Conditions #1

Existing Site Conditions at McMillan Community Center

Existing Site Conditions #2

Existing Site Conditions at McMillan Community Center

Additional Project Information