Project Overview:
The project includes modernizing the existing building, formally known as the Alexander Crummell School, into a new recreation center, building an annex to the existing building, and providing outdoor park amenities to meet the Department’s programmatic requirements.
Project Details:
New Community Center at Historic Crummell School
Address: 1900 Gallaudet St NE
Ward: 5
Construction Agency: DGS
DPR Project Manager: Brent Sisco
DGS Project Manager: Diego Martinez
Project Delivery: Construction Manager at Risk
Architect: Sorg
General Contractor: TBD
Current Budget (Estimate): $20 Million
Project Status: A/E Procurement
Start Date: Design Spring 2023 / Construction TBD
End Date: Summer/Fall 2025
DGS Contact: Wayne Gore
Meeting Information:
Presentations: