Project Description :
The project scope includes the design and construction/General renovations at the Public Safety Communication Center (PSCC) for the Office of Unified Communications located at 310 McMillian Drive, NW the renovations will address ADA compliance, reconfiguration and power / communications upgrade to the roof mounted antenna, a complete replacement of the building systems, upgrade to the workstations, and updating and enlarging the main entrance.
Project Details :
- Address: 310 McMillian Drive, NW
- Ward: 1
- DGS Project Manager: Satish Bagai
- Client Agency Project Manager: Solomon Tadesse
- Project Delivery: Design-Bid-Build
- Status: Construction
- Architect: Alphatec, PC
- General Contractor: Chiaramonte
- Current Budget: $13.5M
- Start Date: Fall 2021
- End Date: Fall 2026
- DGS Contact: Dez Green