Project Description:
This project will consist of the addition of a new recreation center that is attached to the existing Shepherd Elementary School to include a Gymnasium, Multipurpose Room, Fitness Center, Office, Storage Space and bathrooms for both elementary students and adults. The recreation center will be utilized by the elementary school during school hours as their gymnasium and dining cafeteria. Along with the recreation center addition the project will include renovating the school’s existing warming kitchen and cafeteria to a full cooking kitchen and serving area.
Project Details:
Address: 7800 14th Street, NW
Ward: 4
DPR Project Manager: Brent Sisco
DGS Project Manager: Mike Etherton
Project Status: RFP Procurement
Project Delivery: Design-Build
Architect: Bell Architects
General Contractor: MCN Build
Current Budget: $13.4M
Start Date: Fall 2019
End Date: Summer 2020
DGS Contact: Wayne Gore
Shepherd Park Community Center Meeting recording link - June 17th 2021: https://dcnet.webex.com/recordingservice/sites/dcnet/recording/56c4b737b1e9103997560050568c45ba/playback
Shepherd Park Community Center Update - June 17, 2021
Construction Updates:
- Shepherd Park Project Construction Update - September 2020
- Shepherd Park Project Construction Update - August 2020
- Shepherd Park Community Center Construction Update - June 2020
- Shepherd Park Community Center Construction Update - May 2020
- Shepherd Park Community Center Construction Update - April 2020
- Shepherd Park Community Center Construction Update - March 2020
- Shepherd Park Community Center Construction Update - February 2020
- Shepherd Park Community Center Construction Update - January 2020
Presentations:
- Shepherd Park Community Center, August 20th Community Meeting Recording Link: https://dcnet.webex.com/recordingservice/sites/dcnet/recording/playback/fa9f2e0f2d2e445db5a989feef94deed
- Shepherd Park Community Center August 20, 2020 Community Meeting Chat Questions & Answers
- Shepherd Park Community Meeting Presentation - August 20, 2020
- Shepherd Elementary School Community Meeting #5
- Shepherd Park Community Meeting Presentation (August 1, 2019)
- Shepherd Park Community Center Community Meeting Presentation May 23, 2019
- Shepherd Park Community Center Community Meeting Presentation (March 13, 2019)
- Shepherd Park Civic Association Project Update ( May 8, 2018)
- Shepherd Park Community Meeting Presentation (April 17,2018)
Related Information:
- Shepherd Park Community Center GroundBreaking
- Shepherd Park Community Meeting (August 1, 2019)
- Shepherd Park Community Meeting (May 23, 2019)
- Shepherd Park Community Meeting (Aprill 17, 2018)