Short Term Family Housing Construction Projects- Ward3

  Ward: Three

Project Description: The newly constructed Ward 3 STFH program will include fifty (50) STFH family units, computer labs for the residents, administrative space for staff and providers, indoor/outdoor play space, homework/study lounge for residents and other amenities. The site will also include a parking structure to support MPD vehicles and the STFH staff assigned to the site.

Location: 3320 Idaho Ave NW
Name of the Architect:Ayers Saint Gross
Name of the General Contractor:Smoot Construction
DGS Project Manager: Aygei Hargrove
 Project Status: In construction for phase 1 Parking Lot.
Project Start Date: Phase 2 (STFH facility) – Summer 2018
Project Completion Date: Phase 1 – Summer 2018 and Phase 2 – Fall 2019
Construction Management agreement:  see below
Good Neighbor Agreement: Pending. 
 Please direct all inquiries to: [email protected]
For information about the closing of DC General and an overview of the District’s Short-term Family Housing Project, please visit the Office of the Deputy Mayor for Health and Human Services at https://dmhhs.dc.gov//homewarddc

Construction Plans:
Feb 2018 DGS Construction Management Agreement 1-30 (February 5, 2018)

Construction Monthly Updates:

Site Renderings: