Project Description:
Remove and replace existing hospital wards permanent flooring at St. Elizabeth's Hospital.
Project Details:
The Flooring Upgrade (Phase I) at St. Elizabeth’s Hospital involves the removal of existing wood flooring materials and installation of new wood luxury vinyl flooring materials in a total of eleven (11) patient residential pods of the hospital. Provide and install new 9-inch x 59.72-inch-high performance UV-Cured Polyurethane Wood flooring materials with 28 mil (0.7 mm) wear layer thickness and 0.197-inch (5.0 mm) overall thickness.
Address: 1100 Alabama Avenue,
Ward: 8
DGS Project Manager: Emmanuel Nnoli, PE
Project Status: Construction
Project Delivery: Design-Build.
Architect/Engineer: N/A
General Contractor: WKM Solutions, LLC.
Current Budget: $2M
Start Date: August 2021
End Date: October 2023
DGS Contact: Chellese Grove
Presentations: