Project Overview:
The project includes a renovation of the existing Randall Recreation Center, a new pool house, plaza renovation, and additional site improvements.
Project Details:
Address: 820 South Capital St. SW
Ward: 6
Construction Agency: DGS
DPR Project Manager: Nick Kushner / Bria Wigfall
DGS Project Manager: Akia Wells
Project Delivery: Construction Manager at Risk
Architect: Shinberg/Levinas Architectural Design, Inc.
General Contractor: TBD
Current Budget (Estimate): $18.5 Million
Project Status: Concept Design
Design Start Date: Summer 2024
Design End Date: Spring 2025
Construction Start Date: Fall 2025
Construction End Date: Fall 2026 / Winter 2027
DGS Contact: John Stokes
Presentations:
- Randall Recreation Center and Pool Modernization Community Meeting - October 8, 2024
- Randall Recreation Center and Pool Modernization Community Meeting - July 18, 2024