dgs

Department of General Services
 

DC Agency Top Menu


-A +A
Bookmark and Share

Edgewood Recreation Center

Edgewood Recreation Center

Project Overview 

This project will consist of the demolition of the existing community center building and construction of a new, larger, recreation center with a rooftop urban farm. The site will be renovated with new ADA accessible routs, new playgrounds and equipment, addition of a splash pad water feature and a new grass athletic field. Project will also include a full-sized gymnasium. This will be a LEED Silver project.

Project Details

Project Address:  3rd Street NE & Evarts Street, NE
Project Ward:  5
Project Budget:  $18.4M
DGS Project Manager:  Mark Bacus
DPR Project Manager:  Brent Sisco
Architect:  Moody Nolan Architecture
General Contractor: BuleSky/Coakley Williams
Project Start Date: November  2015
Project Completion Date: Spring 2019
Project Status: Construction - Groundbreaking held Jan 2018

Edgewood Construction Update (February 2018)

 

Related Content