dgs

Department of General Services
 

DC Agency Top Menu


-A +A
Bookmark and Share

Hearst Park and Pool Improvement Project

Project Description

The project will include design and construction including, but not limited to, new playground area, new tennis courts, renovation or replacement of existing soccer fields, new pool and pool house, ADA renovations to site, storm water management, remediation of site drainage, runoff, erosion issues, landscaping, fencing, site furnishings amenities, signage and hardscaping.

Project Details

  • Location: Ward 3
  • Construction Agency -  DGS
  • Design Start date  (Park and Pool) –  April 2016
  • Design Completion Date – Winter 2017
  • Construction Start date - Park  - TBD
  • Construction Completion date – Park – TBD
  • Construction Start Date -Pool – TBD
  • Construction Completion Date – Pool -TBD
  • DGS Project Manager: Shahrokh Ghahramani 
  • DPR Project Manager: Peter Nohrden
  • Status: Design
  • Architect: Cox Graae + Spack Architects
  • General Contractor: TBD
  • Budget: Park - $8 Million in FY15-FY17; Pool - $5 Million in FY19
  • DGS Contact: Jackie Stanley (DGS), (202) 431-1195

Hearst Park & Pool Project Community Meeting (February 15, 2017)

 

Related Information